CPIT is currently completing a scoping exercise to determine the size and shape of CPIT’s entry into the Shac 2011 competition.
A brief has been given to students from CPIT’s School of Architecture to scoop and then present to the CPIT Shac committee.
Current thinking on this project is that two units may be built, one with as many alternative and sustainable options available and the other with more conventional practices so the equivalency can be measured.
Features:
One bedroom units that is transportable
Can be placed on a section as a second dwelling
Is easy to relocate as required
Accommodation that meets a range of community needs from emergency housing to a Granny flat.
Services can be connected and disconnected without remedial work required
As self sufficient as possible within a average budget
Wintec have been building two to three bedroom houses with students for the last 24 years these houses are then on sold into the community as affordable housing.
The houses were standard transportable gable or hip roofed hardie blank weather board homes.
These houses were great to build with the students covering all aspects of their learning criteria. The houses were also a popular item within the community requiring a waiting list for perspective buyers.
However Wintec wanted to create a new design that embraced the latest building technologies and current building design trends.
This project and philosophy was shared with the students who designed and built the new mono pitch design.
This was a very inspiring project that fed Wintecs build environment and carpentry department’s philosophy of constant improvement.
Reflection of design and materials was constantly discussed and shared with the students and improvements were implemented and constructed.
These changes were a reflection of what was happening in industry i.e. insulation improvements, double glazing, product changes etc.
Moving forward
It became apparent – and some thing as a school we were very interested in – embracing was the growth and awareness of sustainability and energy consumption within the construction industry.
This interest grew and from that interest two projects evolved within Wintec; The Eco Village and our first entry into the SHAC challenge 09.
SHAC house 09 was a one of design designed within the Built environment school by Trevor Wyatt and built environment students. The project journey was shared within the Shac competition website, students, industry and the community.
Eco Village
The Eco village is another sustainable initiative taking place at Wintec and one we are very excited about. Wintec would like to further develop the eco village house design as our entry into the Shac Challenge 2010.
Further reflecting on the Eco Village house design, as a base model, and making ongoing design, material selection and energy consumption improvements will be part of our continuous improvement philosophy.
Goals
With our involvement in the shac project we would like to showcase some of the exciting developments we have made in regards to imbedding sustainable practices in the construction of the eco village and eco houses. We would also like to:
Make improvements to these developments, (current Eco house design), with student, industry and shac team input. Reflect on the developments made, what was good what was not so good.
Form closer relationships within the trade departments by sharing an overall goal of sustainable design and practices and imbedding this within are current teaching curriculum.
Constantly reviewing materials and product use and investigating more sustainable options.
Creating regenerative communities by;
Demonstrating new residential house technologies re energy consumption.
Contributing an improved house design to the student village community. With emphasis on improved material selection bathroom, WC and laundry layout and better use of internal layout where possible.
Monitoring the Energy consumption of the improved house design and sharing this information for the benefit of the wider community and Shac teams.
Creating a delightful building with emphasis on its surroundings, colours function and creative use of space.
Work with industry and community in achieving our goals.
Vision of regenerative neighbourhood
A regenerative community is a sustainably aware community. The power of education and knowledge is the energy source that will regenerate and power communities for a better future.
Creating a student village as a base model for sustainability, energy consumption research, discussion and debate will ultimately promote the awareness and knowledge required to educate communities and the work force of tomorrow.
Creating an ongoing educational process that promotes the benefits and skills required in the regenerative use of energy, waste, water, fuels, construction materials and techniques are all an integral part of building these communities
Site
The construction of the house will be by Wintec pre trade carpentry plumbing and electrical students at the Avalon campus.
The house will be constructed under cover and transportable. Once completed the house will be relocated to the Eco village site to provide student accommodation and to be monitored for its energy consumption
The site has good orientation to the north with the length of the house located on a east to west axis. The ground profile is soft with a high water table requiring a driven pile foundation.
Building Design
The building design is a 100m2 transportable residential home constructed from building materials readily available and common to the current building market.
Emphasis will be on a multipurpose floor plan a design that can; comfortably accommodate a family of four, be used for shared accommodation purposes’, holiday homes, or be adaptable for class room or community type buildings.
One of the key ingredients in the construction of the house will be the services and facilities we will fit the house out with. This is an area essential to energy consumption and an area we would like to research and monitor.
The building design will be true to its roots with its main objective been to ensure we keep with the fundamentals of our current teaching curriculum in light timber frame construction.
The skills and ability required for the construction of the house are to be associated with the student profile and community type labour resource.
Housing Demand
The ultimate goal is to create a building that is affordable energy efficient and have the ability for multipurpose use.The construction process and material selection will be simple to construct .This will allow small rural community; groups with a small amount of skilled labour and collaborative community know how the ability to; be able to afford and construct houses for families, class rooms for schools, and small community buildings.
Another essential ingredient will be the information and educational resources created by reflecting on the journey travelled in creating the house and student village.
This reflection will continue the philosophy of self improvement and will help advice communities on the what, how and why of creating regenerative communities.
Funding the house build
The estimated cost of the house dependent of foundation design is $1.500 – $1.800 per m2
The majority of the construction labour is to be done by students.
Partial sponsorship by eco village industry partners ECCA and WEL energy.
Supplier sponsorship, (currently) Rinnai hot water systems.
Design support from Rod Yeoman, Ros Epsom, Tina Booth .
Design & Build time lines for short term goals
Working drawings Started 26th July and completed by 13th August. Please note any amendments to design may re start the 20 day consent process and delay stamped approval.
Consented drawings completed by 6th September.
Drawings and construction time schedule to suppliers, sub contractors &, associated tutors 6th September.
16th September start ordering house material for a 4th October construction start.
Design & Build time lines for long term goals
Wintec has a long term goal to continue reflecting on current designs and to further improve current eco house designs and shac 2010 entry.
Concept drawings and collaborative design process completed 08.Sept.2010.
Working drawings completed 08.Oct.2010, sent to council.
Working drawings approved 08.Nov.2010
Working drawings priced, time scheduled and material deliveries programmed by 06.12.2010.
Core Team Members
Tom Malpass – Team coordinator,
E-mail thomas.malpass@wintec.co.nz Ph 07 8348800 ext 8594
Peter Orchard – Construction coordinator, advisor, quality control
E-mail peter.orchard@wintec.ac.nz Ph 07 8348800 ext 8594
Nathan Collins – Design coordinator.
Werner Eisenhower – Plumber & plumbing waste water system coordinator
Tina Booth – Team Architectural Draughts person
Ros Epsom – Team Architect,
Annette Vincent – Team Quantity surveyor embedding sustainability into current curriculum
Rob Sweet – Student village spokesman
Lukas Maree – Team electrician & electrical coordinator
Ian Mayes –Eco house advisor and Hamilton council representative
Students
The Proposal
It is proposed to build a Southland Sustainability Learning Centre – EcoDen.
Vision
The Southland Sustainability Learning Centre – EcoDen is a facility that promotes, motivates and encourages all sectors of the community to be environmentally sustainable, emphasising resource stewardship, energy efficiency and waste minimisation.
Goals
Demonstrate sustainable design and building practices
Demonstrate sustainable living practices in its activities, but also within its features such as displays and demonstration areas.
Demonstrate waste reduction, reuse, recycling and recovery of resources
An educational facility that caters for all ages from preschool to adults i.e. Field trip location, sustainable living classes, training facility for teachers and staff, natural building workshops etc.
The suggested location for the EcoDen is on vacant land at the Invercargill Waste Transfer Station, owned by the Invercargill City Council. It is proposed that the facility be owned by an established charitable trust to aid in securing public funding and operated by WasteNet Southland. Background
In 2008 a series of Sustainable Living workshops took place, set up by Invercargill City Council, Environment Southland and Southland Education. Topics included No Weeds in the Vege Patch, Solar Energy, Recycling and Alternative Fuels.
The popularity of theses indicated that the timing was right to run further workshops. A barrier to running these courses were the limited practical examples located in the one facility or venue. To overcome this barrier, an idea evolved to develop a demonstration garden with an eco-classroom to cater for all weather conditions – hence EcoDen.
The idea has further been developed into one facility that caters for all sectors of the community from preschool to adult education.
There is also a need to raise public awareness of sustainable building, and to stimulate the professionals and trades involved in the building industry to make continuous improvements in this area. Particularly as Southland prepares for continued economic growth and population growth, new buildings are expected to be built, and as a region we need these to be sustainable, and as energy efficient as possible.
The EcoDen project leads itself as an opportunity for highlighting champions (developers, designers, retailers, builders and other trades). The EcoDen could include a commercial display space for different products, which could generate income for the facility to cover operational costs, as well as showcasing the products and design aspects used in the building itself. Project Team
The following key project team roles have been identified:
Role
Name / Organisation
Team coordinator
Donna Peterson, Invercargill City Council and WasteNet Southland
Designers
Craig Haywood, Design Base
Phil Orr, ArchDraught
Project Manager (for the build)
Mike Grumball SIT
Communication
To be confirmed
Funding coordinator
To be confirmed
Partners
The following outlines some of the potential partners in this project and indicates their potential involvement.
Potential Partners
Involvement (in bold if confirmed)
Invercargill City Council
Landowner
Education programmes
Arrange lease for building owner
Wastenet Southland
Lodge SHAC Entry
MOU for partners
Potential funding?
Education programmes
Venture Southland
Assistance with preparing funding applications
Assist with seeking VS Charitable Trust approval for ownership Communications – promoting sustainable practices within building industry
Stonewood Homes – Brent Mettrick
Brent@stonewood.co.nz
?
Resene
?
Placemakers – Derelle
?
Cunningham Builders – Kevin
?
Transition Towns
?
Thermocell
Supply of solar water heating?
Other commercial partners
TBC
Draft Timeline
Date
Milestone
2 August 2010
Submit SHAC entry for EcoDen
27 August 2010
Confirm Project Team Members, clarify vision and goals (using the Integrated Design Process).
1 September 2010
Deadline for EOI for Funding (Community Trust of Southland)
27 September 2010
Proposed design(s) completed and budget confirmed
1 October 2010
Regional Workshop
28 October 2010
Design finalised, vision/goals and budget revised as necessary
31 October
Grant Application for CTOS
20 November 2010
Develop detailed plans
28 November 2010
Project Development and Documentation submitted to SHAC
February 2011
Presentation to CTOS
March 2011
Funding confirmed
March 2011
Apply for resource/building consents as appropriate
April 2011
Construction begins
September 2011
Construction complete
October 2011
National Conference
Funding